Saturday, October 2, 2010

Update

Hello again....we are on the homeward stretch but not yet been given a handover date.

Since last blog:

  • tiling in bathrooms, laundry completed;
  • toilets and bath installed;
  • majority of plumbing completed;
  • electricians back in - installed alarm, power points, exhaust fans, IXL Tastics, rangehood, light outlets, downlights;
  • tiling to main downstairs floors commenced - hope to be finished on Tuesday
Met with J our SS on Friday - unfortunately there has been an issue between gyprockers/electricians - no marks on ceilings as to where wiring for lighting is which will lead to repairs to gyprock. Also, step in pantry not correct - needs to be fixed.

Next week:
  • tiling to main downstairs floors to be completed;
  • insulation to be fitted;
  • air conditioning to be completed;
  • upstairs floor sanding;
  • electricals to be completed;
  • plumbing to be completed;
  • gyprock repairs;
  • hopefully - measurements will be taken for shower screens so these can be installed asap.

Once the above has been done, cleaners can then come back in and do a thorough clean before painters come in again.

Last word from R our landscaper, is that our DA is in neighbour consultation stage which will finish on 13 October and approval should issue within a week - hopefully R will be available to commence landscaping works asap after approval issued.

Perhaps we should start the packing yet again!!!