Since our last blog:
  • tiling to main downstairs floors completed;
  • insulation fitted;
  • air conditioning completed - despite a minor hiccup with cutting of grills;
  • upstairs floor sanded;
  • electricals completed - despite a couple of issues with positioning of light fittings;
  • plumbing completed;
  • gyprock repairs completed;
  • shower screens measured;
  • downpipes connected;

What's left to be done before handover:
  • shower screen installation
  • carpets to be laid
  • handrails to stairs to be fitted
  • wardrobe and pantry fittings
  • thorough clean up inside and outside
  • driveway and alfresco area
Practical completion inspection booked for Tuesday 26 October and handover should be sometime either on or or before 5 November 2010.

Not long now......