- tiling to main downstairs floors completed;
- insulation fitted;
- air conditioning completed - despite a minor hiccup with cutting of grills;
- upstairs floor sanded;
- electricals completed - despite a couple of issues with positioning of light fittings;
- plumbing completed;
- gyprock repairs completed;
- shower screens measured;
- downpipes connected;
What's left to be done before handover:
- shower screen installation
- carpets to be laid
- handrails to stairs to be fitted
- wardrobe and pantry fittings
- thorough clean up inside and outside
- driveway and alfresco area
Practical completion inspection booked for Tuesday 26 October and handover should be sometime either on or or before 5 November 2010.